New Home Plans in Pebble Beach, CA
New houses and teardown rebuilds in the Del Monte Forest, drawn for Pebble Beach Company’s design review, Monterey County’s coastal permits, the Pebble Beach fire and sewer rules and the Peninsula water permit.
Quick version: Building a new house in Pebble Beach means two separate approvals for the same design. Pebble Beach Company looks at it first under the deed restrictions that cover the Del Monte Forest, and Monterey County then issues the coastal permit and the building permit. Around those two sit four more checks: the coverage and slope limits in the County’s Del Monte Forest rules, the Pebble Beach fire conditions, the community services district’s sewer permit, and the water permit, which in the Del Monte Forest often turns on whether the lot carries a water entitlement. We sort those out before drawing a floor plan. Call 805-712-8993.
Two approvals, in this order: the Company, then the County
Pebble Beach Company and its predecessors granted the deeds and CC&Rs for land in the Del Monte Forest, and those deed restrictions give the Company’s design review board, known locally as the ARB, the authority to approve, condition or reject plans for homes and site work. The Company’s Del Monte Forest residential standards and guidelines (effective April 1, 2022) describe how the board works:
- Who decides: six members, five of them Del Monte Forest property owners appointed by the Company and a Company senior executive as chair. Three votes approve a design.
- What it weighs: size, design, compatibility with neighbors, disturbance of terrain and vegetation, setbacks, materials and exterior color. The guidelines favor a house that sits in harmony with its surroundings over one that dominates the street.
- How long: the board generally responds within 30 days of a complete submittal, in writing, with approval, conditional approval, disapproval or a continuance. Approval lapses after one year unless work has started or the board grants an extension.
- What it is not: Company approval does not assure County or Coastal Commission approval, and the owner still has to secure every public permit.
The Company’s own process notes recommend sending plans to its board before the County, so that any design changes it asks for are made before County planners see the project. Where the County and the Company set different setbacks, the stricter one applies. The Company’s review office also keeps residential files with the original house plans for most Del Monte Forest properties, which is the first place we look on a teardown or a lot next to an older home.
What the Company’s checklist asks for
The Company publishes a preliminary and a final submittal checklist (dated April 1, 2022), posted with the guidelines on the Del Monte Forest Property Owners links page. Before staff will even begin the first look, a new residence, a demolition or a second-story addition has to be staked and flagged on the lot. Incomplete sets are returned. For the preliminary submittal, one set no larger than 24 by 36 inches plus an emailed PDF:
- Site plan at 1/8 inch scale where possible: property lines, existing and proposed structures and driveways with dimensions to the lines, one-foot contours (two-foot outside the building area on large, steep lots), easements and setbacks, cut and fill in cubic yards, a drainage and erosion plan showing effects on neighbors and roads, the service yard, underground utilities and the direction of the main view.
- Trees: every native tree over 5 inches in diameter measured two feet above the ground, with removals marked and tallied by type and size, plus neighboring trees the work could affect.
- Numbers: lot size, existing and proposed square footage, lot coverage percentage and floor area ratio.
- Elevations drawn to scale (rendered or sketched elevations are not accepted), with existing and finished grade, the road level, every material called out, and the maximum height measured from the average ground elevation under the footprint to the top of the roof.
- Other sheets: a roof plan with the roofing sample, floor plans, a typical wall section from eave to foundation, paint and material color samples, a color rendering of the street elevation for new homes, and exterior light locations with fixture cut sheets and the light pattern. A landscape plan is optional; the lot may stay natural.
The final submittal adds the dimensioned floor plans with door and window sizes, plumbing fixtures, the furnace and water heater, the electrical and mechanical layout, the mapped grading area and a construction schedule with work hours. Staff can sign off a final set that matches the preliminary approval; a set that changed significantly goes back to the board.
Size, height and setbacks on a Del Monte Forest lot
The Company’s process sheet includes a summary of the zoning numbers it sees most often. County zoning controls, and some deeds and subdivision maps are stricter, so we treat this as a starting point and confirm each lot with the County and the review office:
- MDR/2 (up to two units per acre): 25 percent floor area ratio, 25 percent site coverage, 27-foot height, side yards of 10 feet on the first floor and 20 on the second, rear yard 10 feet.
- MDR/4 (up to four units per acre): 35 percent floor area ratio and 35 percent coverage, with the same 27-foot height and yard numbers as MDR/2.
- LDR (low density, about one unit per 1.5 acres): 15 percent coverage, 20 percent floor area ratio on LDR/1.0 and 17.5 percent on LDR/1.5 to 2.0, a 30-foot height and 20-foot side and rear yards.
- Front yards vary with the width and location of the road, so both offices are called before design.
Definitions matter. In that summary, floor area is measured to the outside stud face of the exterior walls, and a basement that meets the building code definition is left out. Site coverage counts decks or terraces 24 inches or more above the ground and eaves that project more than 30 inches. On a half-acre MDR/2 lot of 21,780 square feet, 25 percent works out to about 5,445 square feet of floor area, before any watershed limit is applied.
The guidelines add their own limits: the main house may not exceed 30 feet, some subdivisions hold it to 27, and certain lots are restricted by deed to a single story. Accessory buildings stop at 15 feet and ADUs at 16. Every house needs an enclosed garage for at least two cars plus two more spaces on the lot, with no carports and no parking on the road. Each property gets one driveway entrance, circular drives are a last resort, and a driveway steeper than 25 percent is not allowed. The board looks for earth-tone colors, non-reflective finishes, flat low-profile skylights and restrained, shielded exterior lighting, and every roof must meet Class A fire standards.
Monterey County coastal permits in the Del Monte Forest
Pebble Beach is unincorporated and in the Coastal Zone, so the County weighs a new home against the Del Monte Forest Land Use Plan and its Coastal Implementation Plan (Part 5 of the County’s coastal zoning). The County’s Del Monte Forest plan page lists the plan, its figures, the implementation plan and a list of background reports required in the Del Monte Forest.
A County Planning Commission file from 2022 for a new two-story house on a quarter-acre lot zoned MDR/4-D shows how the pieces fit together:
- A single-family home in the MDR zone needs a Coastal Administrative Permit, and the “D” design control overlay adds a Design Approval covering location, size, configuration, colors and materials.
- Removing protected trees takes a separate Coastal Development Permit under the Del Monte Forest tree rules. In that case, three of the eight trees removed were landmark Monterey pines over 24 inches in diameter, so an arborist report and a replanting condition were part of the file.
- The Del Monte Forest Land Use Advisory Committee looked at the materials and colors before the hearing, and the lot was flagged and staked.
- Staff confirmed on a site visit that the house could not be seen from public viewing areas such as 17-Mile Drive or Huckleberry Hill.
The County’s design approval matrix is a guide to the level of review by project type, with the zoning text controlling where they differ, and it reminds staff to check viewshed policies on every project. For coastal parcels, the Coastal Commission’s appeal information sheet lists where a County coastal permit can be appealed to the Commission, including development between the sea and the first public road paralleling it, within 300 feet of the beach, within 100 feet of a wetland or stream, and within 300 feet of the top of a coastal bluff. Ocean-side lots along 17-Mile Drive can fall in those areas, so we check early.
The Pescadero watershed coverage cap
The southern third or so of the Forest drains through the Pescadero watershed to Carmel Bay, a state Area of Special Biological Significance. As a 2017 Coastal Commission staff report on a Del Monte Forest appeal explains, Section 20.147.030 of the implementation plan limits residential impervious coverage there, buildings and site improvements together, to 9,000 square feet. It also asks every new project in the watershed to keep driveways to the shortest, narrowest layout that gives simple, direct access, keep other paving to daily parking needs, and use permeable materials and filtration where they help. On a large lot, that cap can control the design more than the floor area ratio does, so we total the roof, driveway, motor court, terraces and walks from the first sketch.
Steep slopes and trees
The same report quotes Land Use Plan Policy 78: development on slopes of 30 percent or more is prohibited unless that siting better meets the plan’s objectives than the alternatives on gentler ground, and a geotechnical report for building on such slopes is filed with the coastal permit application. On the Company’s side, no tree may be removed without both a Company tree permit and County approval, with Monterey pine, Bishop pine, coast live oak, Monterey cypress and Gowen cypress singled out for protection. Where a foundation has to go inside a tree’s drip line, the guidelines call for piers and grade beams.
Fire: the Pebble Beach Fire Department’s conditions
The Pebble Beach Community Services District runs the Pebble Beach Fire Department, and its 2025 Fire Defense Plan, prepared with CAL FIRE, notes that no open space in the Forest is more than a mile from a home, so the whole Del Monte Forest can reasonably be treated as wildland-urban interface. New buildings must meet the fire code’s exterior materials standards for those areas. You file with the County, and per the Fire Prevention and Planning office that serves Pebble Beach, Cypress and Carmel Highlands, the County forwards the set it has checked to that office for fire review. Its new residential conditions include:
- Fire sprinklers in every new residential project, covering the house and attached garage. At least four sets of sprinkler plans from a C-16 contractor are approved before installation, and the rough sprinkler inspection comes before the framing inspection.
- A household fire warning system under NFPA 72, designed by a C-10 contractor and approved before installation.
- Driveways at least 12 feet wide with 15 feet of vertical clearance, no steeper than 15 percent, with a heavier paving section over 8 percent and a surface that carries a 22-ton engine. Drives over 150 feet need a midpoint turnout and a turnaround within 50 feet of the house.
- Gates set back at least 30 feet from the road, at least 12 feet wide, with a key switch on electric gates.
- Address signs at each driveway entrance, reflective, with 4-inch numbers readable from both directions, posted when construction starts.
- Defensible space managed to 100 feet or the property line, limbs trimmed to 6 feet, and nothing within 10 feet of a chimney.
- A Class A roof on every new structure.
Final fire clearance checks the sprinklers, the alarm bell outside the primary bedroom, the driveway slope, the gate switch, vegetation clearance, address numbers and smoke alarms. For the parcel’s hazard zone, the State Fire Marshal’s fire hazard severity zone maps cover state responsibility areas (effective April 1, 2024) and local areas (released in 2025). The code edition that applies depends on the submittal date, so we confirm it with plan check.
Sewer: the community services district permit
Sewer service comes from the Pebble Beach Community Services District. Its sewer permit page asks owners, contractors or plumbers to fill out the sewer permit application and email it to the District, and the plumber doing the work has to be on the District’s current registered list. The application covers new connections, demolition and capping, reconnections, lateral replacement and septic bypass, so a teardown rebuild usually involves more than one of those boxes. The District’s lateral and inspection requirements set the standard for every home:
- one independent lateral per dwelling, in PVC, ABS or HDPE, at least 4 inches across with 3 feet of cover at the property line;
- a sewer relief valve for each dwelling and cleanouts every 100 feet;
- no connections to manholes or interceptors, and the connection to the main made by District staff only;
- inspection before any backfill, requested at least 24 hours ahead, with a camera inspection in front of District staff when a trenchless method is used.
Water: Cal Am service and the water management district permit
Water in Pebble Beach is delivered through the system owned and run by California American Water (Cal Am), and the Monterey Peninsula Water Management District decides how much new use a property may add. Its water permit page says a permit is needed for any new connection, including a new home, and for added fixtures, pools and new landscaping. The district’s application process runs after County plan check:
- plans that meet the district’s water efficiency standards, with landscape plans and a water budget for new construction;
- a Water Release Form signed by the County, then complete stamped plans sent to the district (concept plans are not accepted);
- a fixture inventory inspection if none is on file, and deed restrictions signed before a notary and recorded with the County Recorder;
- the water permit carried back to the County to get the building permit, and a separate district final inspection when the house is done.
The district’s Rule 142.1 applies its landscape standards to new construction, including demolition projects, with 500 square feet or more of new landscape, and requires the performance method once the landscape reaches 2,500 square feet.
Where the water comes from: entitlements and the moratorium
New Cal Am connections on the Peninsula remain under a State Water Board moratorium. The district’s cease and desist order page reports that it asked the Board in October 2025 to lift it, that the Board opened a hearing in June 2026, and that a public comment day is set for November 5 with closing briefs due November 10. The Del Monte Forest has its own path around that: the Pebble Beach Company entitlement. Under the district’s Rule 23.5, those water use permits are a vested property interest in a set amount of water for specific benefited properties, and they are not cancelled or reduced by a moratorium on new meters. Each permit states the type of use, the number of connections and the amount of entitlement tied to the lot, and an owner who bought entitlement from the Company may use it only on that parcel.
On a teardown, the existing connection and fixtures matter too. The district’s water credits page explains that credits are documented when fixtures are permanently removed, including by demolition, and that water use credits expire after ten years. Before a single fixture is placed, we want to know which of these applies to your lot and how much water it represents.
What goes in a Pebble Beach new-home plan set
The County’s building permit submittal requirements for a new single-family home call for every sheet signed and dated in ink by the preparer, the job address on the first sheet, a complete site plan and construction set (the County forwards it to every agency that has to check it), structural calculations stamped by a licensed engineer, Title 24 energy calculations, truss plans and calculations (which can be deferred until before the trusses go up), a geotechnical report and a soils engineer’s review letter. For a Pebble Beach house we typically prepare:
- Survey-based site plan: setbacks from the deed, map and zoning, tree locations with sizes and removals, slope bands at 30 percent, the impervious coverage tally for Pescadero lots, the fire driveway layout with turnouts and turnaround, utilities and the sewer lateral route.
- Company sheets: elevations with average-grade height, the wall section, roof and color samples, the street-elevation rendering and the lighting plan.
- County sheets: floor plans, elevations and sections, grading and drainage, and erosion control.
- Engineering and energy: structural plans and calculations from a licensed engineer, Title 24 compliance, and the deferred sprinkler and alarm submittals.
- Water sheets: the fixture count and the landscape and irrigation plans the water management district needs.
How a Pebble Beach new home moves with us
- Lot research: zoning and overlays, deed limits, the Company’s property file, the watershed, slopes over 30 percent, protected trees, the fire hazard zone, and the water entitlement or existing connection.
- The numbers: floor area ratio, coverage, the Pescadero impervious total where it applies, height from average grade and the fire driveway geometry.
- Concept and staking: site plan, massing and elevations, staked and flagged on the lot for the Company’s first look.
- Company preliminary review, then the County application for the Coastal Administrative Permit, Design Approval and any tree permit, with the advisory committee meeting.
- Final sets: the Company’s final submittal and the County building set, followed by the water permit, the sewer permit and the fire submittals.
- Construction: our sister company Harrod Built can give you costing as the design comes together and build it when your plans are approved.
Our work and the plan set
We are a Paso Robles design office, and the plan sets we show are homes in North San Luis Obispo County, not Del Monte Forest projects. Our Modern French Country home in Templeton pairs the full set with photos of the finished house. Under Business and Professions Code 5537, a designer like us may prepare plans for wood-frame houses of up to two stories plus a basement. Licensed engineers design and stamp the structure and the geotechnical work, and we bring in the licensed professionals each agency asks for, such as a surveyor for the staking or an arborist for the tree report.
Pebble Beach new home questions
Do I need Pebble Beach Company approval before applying to the County?
In practice, yes. The deeds and CC&Rs in the Del Monte Forest require the Company’s design review board to approve property improvements before the owner can get Monterey County permits, and the Company strongly recommends submitting to its board before the County so any changes it asks for are made first. Its approval does not replace County or Coastal Commission approval.
How big can a new house be on a Pebble Beach lot?
It depends on the zoning and the deed. The Company’s zoning summary lists floor area ratios of 25 percent in MDR/2, 35 percent in MDR/4 and 20 or 17.5 percent in low density lots, with matching site coverage limits of 25, 35 and 15 percent. In the Pescadero watershed the County caps residential impervious coverage, buildings and paving together, at 9,000 square feet. We run both sets of numbers for your parcel before design starts.
What County permits does a new Pebble Beach home need?
Pebble Beach is in the Coastal Zone of unincorporated Monterey County. A recent County file for a new house on a quarter-acre MDR lot combined a Coastal Administrative Permit and Design Approval for the house with a Coastal Development Permit to remove protected trees, heard by the Planning Commission after the Del Monte Forest Land Use Advisory Committee looked at the materials and colors.
Are fire sprinklers required on a new home in Pebble Beach?
Yes. The Fire Prevention and Planning office that serves the Pebble Beach Community Services District requires sprinklers in all new residential projects, with plans from a C-16 contractor approved before installation. The house also needs a household fire warning system, a Class A roof, and a driveway at least 12 feet wide that stays at or under 15 percent grade.
Can I get water for a new house in Pebble Beach?
The answer depends on the lot. The State Water Board moratorium on new Cal Am service connections is still in place while the water management district’s request to lift it is heard. Pebble Beach Company water entitlements under the district’s Rule 23.5 are a vested right on specific benefited properties that a moratorium does not cancel, so we check whether your parcel holds one, or an existing connection, before design.
Who handles the sewer connection in Pebble Beach?
The Pebble Beach Community Services District. Its sewer permit application is emailed to the District, the plumber must be on its registered list, District staff make the connection to the main, and every lateral is inspected before backfill with at least 24 hours’ notice.
Related: home design and drafting in Pebble Beach, Monterey County, Carmel-by-the-Sea, Carmel Highlands, Carmel Valley, Pacific Grove, Monterey, Carmel remodel plans, new home plans in Montecito, custom home design, ADU plans in Monterey County, new home plans in Carmel Valley, new home plans in Carmel-by-the-Sea. Guides: what’s in a permit set, areas we serve. Working on an existing house? See remodel and addition plans in Pebble Beach.
Ready to build in the Del Monte Forest?
We design with real construction costs in mind, and our sister company Harrod Built can give you costing as the design comes together and build it when your Pebble Beach plans are approved. Same family, same office.
Nearby custom home guides: custom home design in Pacific Grove, custom home design in Monterey and custom home design in Big Sur.
Get a quote for new home plans in Pebble Beach
Call 805-712-8993, or use the form below with the street address or parcel number, any survey or arborist report you already have, and a short note on the house you have in mind. You can also reach us on the contact page.
Sources for this page: Monterey County’s Del Monte Forest plan page, design approval matrix, building permit submittal requirements and a 2022 Planning Commission file; a 2017 California Coastal Commission staff report quoting the Del Monte Forest implementation plan, and the Commission’s appeal information sheet; Pebble Beach Company’s Del Monte Forest residential standards and guidelines and submittal checklist (April 1, 2022, as posted by the Del Monte Forest Property Owners); the Pebble Beach Community Services District’s sewer permit pages, application, lateral requirements and 2025 Fire Defense Plan; the Fire Prevention and Planning office’s building permit page and new residential conditions; the State Fire Marshal’s hazard zone page; and the Monterey Peninsula Water Management District’s water permit pages, Rules 23.5 and 142.1, cease and desist order page and water credits page (checked October 17, 2026). Rules change, so we confirm with the County, the Company and each district for every property before design.