ADU Plans in Sand City, CA

ADUs and junior ADUs on Sand City’s residential and mixed-use lots, drawn to Chapter 18.63 and the City’s zoning compliance statement process.

Quick version: Sand City is small, and most of its homes sit in a few neighborhoods and its mixed-use areas. ADUs are approved through a zoning compliance statement from the City Planner, then a building permit. The City’s chapter has a few rules that are stricter than state law, so we confirm how the City applies them before drawing. Call 805-712-8993.

How Sand City approves an ADU

The City’s ADU page lays out three steps: review the ordinance, apply to the Planning Department for a zoning compliance statement, then pass a ministerial exterior design check and building permit review. The rules are in Chapter 18.63 of the municipal code, last amended by Ordinance SC 25-01 (February 18, 2025).

  • Where: all areas that allow single-family or multifamily homes, including the Planned Mixed-Use (MU-P) district; existing commercial buildings in MU-P may add one ADU and one junior ADU.
  • How many: one ADU and one junior ADU on a single-family lot; multifamily lots follow the state counts.
  • Timing: the zoning compliance statement within 60 days of a complete application when a house exists, without a hearing.
  • Septic: Monterey County Health Department approval where a private sewage system is used.

Size, height, setbacks and parking

  • Size: detached up to 1,200 square feet, or 1,000 square feet with more than one bedroom; attached up to 50 percent of the existing house; junior ADU up to 500 square feet.
  • Height: detached 16 feet, or 18 feet near a major transit stop, high-quality transit corridor or on a lot with a multistory multifamily building, plus 2 feet to match the house’s roof pitch; attached 25 feet or the zone limit, whichever is lower.
  • Setbacks: none for converted existing space or a same-size rebuild; no more than 4 feet from side and rear lines for new units.
  • Parking: at most one space per unit or bedroom, tandem or in a setback allowed; none near transit, in existing space, or when a garage is converted or torn down for the ADU; none for a junior ADU.
  • Design: same exterior style, materials and colors as the house, checked ministerially before the building permit.

Rules we confirm with the City first

Sand City’s 2025 code requires the applicant to be the owner-occupant and records a deed restriction tying occupancy to the owner. The State Department of Housing and Community Development sent the City a letter in October 2025 saying its records show the ADU ordinance out of compliance with state ADU law and listing the recent state changes. State law does not allow owner-occupancy rules for ADUs (it still does for junior ADUs that share a bath). Before you count on renting both the house and the unit, we ask the City in writing which rule it applies.

Lots west of Highway 1, and a 200-foot strip east of it, are in the coastal zone under the City’s code, so a project there also goes through the City’s Local Coastal Program. Water and sewer follow the Monterey Peninsula Water Management District’s fixture rules; the district’s ADU page explains the count.

What goes in the application

  • the zoning compliance statement application to the Planning Department;
  • site plan with lot lines, the house, the ADU, setbacks, parking or the transit distance, and utilities;
  • elevations showing the matching exterior style, materials, colors and height against the house;
  • floor plans, sections, structural sheets from a licensed engineer and Title 24 energy compliance for the building permit.

Who draws the plans

Harrod Drafting & Design is a Paso Robles drafting and design office. The plan sets on our portfolio are homes in North San Luis Obispo County; we have none to show in Sand City yet. To judge the drawings, see our portfolio or our sheet-by-sheet permit set guide. State law (Business and Professions Code 5537) allows a building designer to prepare plans for wood-frame dwellings of two stories or less plus a basement, which covers ADUs, garage conversions and most single-family homes; a licensed engineer designs and stamps the structure, and we bring in a surveyor, arborist or other consultant when the lot calls for one.

Sand City ADU questions

Does a remodel in Grover Beach need the full major permit checklist?

Only some do. The City’s Major Building Permit Checklist covers additions and alterations that involve structural changes. A remodel that moves bearing walls, changes beams or adds area falls under it; a cosmetic kitchen or bath update without structural work usually does not.

When does a Grover Beach remodel need a soils report?

The checklist requires a geotechnical soils report for additions over 500 square feet and for new structures.

Do the objective design standards apply to a remodel?

They apply to additions over 500 square feet. If the remodel adds an upper floor, the 80 percent upper-floor rule and the facade articulation items come into play.

How long is plan check?

The checklist lists 20 business days for the first check and 15 business days for later rounds.

Do I need a coastal permit to remodel?

West of Highway 1, any project in the coastal zone needs a coastal development permit. East of Highway 1, additions on single-unit lots in the coastal zone go through an administrative coastal permit; interior-only work usually does not.

Related: ADU guides for Seaside, Marina, the City of Monterey, Pacific Grove, Carmel-by-the-Sea and unincorporated Monterey County, plus garage conversion plans in Monterey County, the Monterey County hub and all the areas we serve.

Ready to start the ADU?

We design with real construction costs in mind, and our sister company Harrod Built can give you costing as the design comes together and build it when your Sand City plans are approved. Same family, same office.

Get a design quote in Sand City

Call 805-712-8993 or use the form. It helps to include the address or parcel number, the lot size, any garage or studio you want to convert, the trees near the spot you have in mind, what you know about the property’s water, and the unit size you want. Our contact page lists other ways to reach us.











    Sources for this page: City of Sand City ADU page and Ordinance SC 25-01 (Chapter 18.63 and the coastal zone definition in Chapter 18.04); the State HCD letter to Sand City (October 2025) and ADU Handbook; and the Monterey Peninsula Water Management District’s ADU page (checked October 23, 2026). We confirm each item with the City for every parcel before design.