ADU Plans & Permit Drawings in Salinas, CA
Site plans for the City’s pre-approved units, plus custom backyard cottages, attached units, junior ADUs and garage conversions drawn for Salinas Paperless Permits.
Adding a second unit behind a Salinas house usually comes down to one choice: build one of the City’s four ready-made detached designs, or have a unit drawn for your lot. We prepare the drawings for either route from our Paso Robles office, and we size every option against the rules the City actually applies today, which changed in 2026. Before anything else we confirm the parcel is inside City limits; some addresses with a Salinas mailing address sit in unincorporated Monterey County, and those go to the County instead (see our Monterey County guide and ADU plans in unincorporated Monterey County). For Gonzales, Soledad, Greenfield and King City, see our Salinas Valley ADU guide.
Which ADU rules apply in Salinas right now
On February 24, 2026 the City Council adopted Ordinance 2693 (Zoning Code Amendment 2025-001). It deleted the City’s own ADU section, 37-50.250, and rewrote the zoning tables so that ADUs are “permitted pursuant to State ADU law.” The ordinance explains why: the old section had not kept up with state law, and the state housing department recommended following state law directly until the City writes a compliant replacement as part of its zoning code update.
That matters for design, because some limits disappeared with the old section. It had, for example, barred an ADU that needed new floor area on the second floor of a house. Today the City reviews applications under the state framework in Government Code 66314 and the sections after it. A broader Phase 1 zoning update aimed at aligning the code with state housing law cleared the Planning Commission on July 15, 2026. We check where that stands when your project starts.
State standards we design to inside City limits
- Size: a detached unit up to 1,200 sq ft; an attached unit up to half the floor area of the existing house (Gov. Code 66314).
- Setbacks: no more than 4 feet from side and rear lines for new construction. A conversion of existing space, or a rebuild in the same spot and to the same dimensions, needs no setback. The City notes that at 5 feet the walls facing the line don’t need fire-resistive construction, so we compare both before locating the unit.
- Height: at least 16 feet for a detached unit, 18 feet within a half-mile walk of a major transit stop or high-quality transit corridor plus 2 feet to line up with the main roof pitch, and up to 25 feet (two stories) for an attached unit, capped by the zone’s height for the house (Gov. Code 66321).
- Parking: no more than one space per unit or per bedroom, whichever is less, and tandem spaces on a driveway count.
- Sprinklers: only if the existing house is required to have them, and building the ADU doesn’t make the house add them.
The City’s four ready-made ADU designs
The City’s ADU program, prepared with Design Path Studio, offers four floor plans, each available with a Spanish, Ranch, Mid-Century or Craftsman exterior: 1A and 1B are one-bedroom, one-bath units of 495 and 553 sq ft, 2A is a two-bed, two-bath unit of 749 sq ft, and 2B is a two-bed, one-bath unit of 746 sq ft. Exterior materials are selectable, but the finished unit still has to follow the design of the main house. They are for brand-new detached ADUs within City limits only, so an attached unit or a conversion can’t use them.
From October 1, 2026, new applications must use the 2025 editions of these sets; the 2022 editions now sit in an archive. If you downloaded a set before that, check its date before relying on it.
Steps for a pre-approved unit
- Planning meeting. Current Planning has to meet with you before any building permit is filed. Appointments are booked through Qless, or call the ADU Hotline at 831-758-7208.
- Site plan and paperwork. Along with the chosen set, its cover page filled in, the package includes the permit application, the City’s form for construction and demolition debris, an owner-signed hold harmless statement, the full grant deed, a site plan and California solar and energy paperwork. The City’s own list suggests hiring a building designer for the site plan; that sheet, and the energy coordination, are our part.
- Online filing. Everything goes through the City’s paperless permit portal; there is no paper option.
- Deed restriction. Every owner, plus the City planner, signs and notarizes a deed restriction, and the County of Monterey Recorder’s Office records it before issuance; the City allows up to three weeks for this. The same step applies to custom units, so we flag it early and it runs alongside plan check.
What the City’s 2026 ADU checklist asks for
A custom unit is reviewed against the City’s New ADU Checklist (March 2026), built on the 2025 California codes. Sheets go in as signed, dated, print-ready PDFs, one sheet per file, landscape, at 24 x 36 or 30 x 42 inches, with no password or edit locks. Each sheet name starts with a discipline letter (S for structural, for example) and says what the page shows.
- A cover sheet with the preparer’s details, the parcel number and owner, a scope of work, project data (construction type, occupancy, area, height, stories, sprinklers yes or no), a sheet index and a deferred submittal list for trusses, sprinklers or solar.
- A site plan with the roofline and every projection dimensioned to the property lines, plus gates, walls, fences, driveways, easements, utilities and meter locations, and a vicinity map.
- For conversions, a demolition plan and detailed plans of the existing part of the building being converted.
- Elevations of all sides with materials and mechanical equipment, foundation, roof framing and braced-wall or shear-wall plans, an electrical plan with panel schedules and a single-line diagram, and a gas line diagram with calculations.
- Energy compliance forms and the CALGreen mandatory measures checklist printed on full-size sheets, plus structural calculations and a special inspection form when required.
The soils questions on the cover sheet
The checklist asks every ADU set to carry a short soils and foundation table on the cover sheet. It asks whether the site is flat, whether a detached unit is a single story, whether the total area is under 1,200 sq ft, and whether the work is near ascending or descending slopes steeper than 35 percent. It also asks about basements, retaining walls, pools, deep foundations and known geotechnical hazards. A “shaded” answer means the City needs more information, which can mean a soils report. We fill the table in from the site visit and your lot’s records so there are no surprises at plan check.
Sign-offs outside the Building Division
Planning, Fire and Engineering may each review an ADU depending on its scope. Before the permit is issued, the City also wants proof from Monterey One Water, which handles sewer capacity, and from your school district, in the form of a receipt or waiver from each. If the unit needs a new or larger water meter, we first confirm who supplies water to your parcel. Where it is Cal Water’s Salinas District (254 Commission Street), its Application for Metered Service asks for lot size, structure size, number of floors, the elevation difference from the meter and the pipe size past the meter.
Junior ADUs and garage conversions
A single-family lot in Salinas can carry a detached ADU and a junior ADU together, with the junior unit built within the home’s existing footprint or its attached garage. Under Gov. Code 66333 as amended effective January 1, 2026, the owner has to live on site only when the junior unit shares a bathroom with the house. It still needs a recorded deed restriction, its own entrance, an efficiency kitchen and rentals longer than 30 days.
A garage conversion can’t use the pre-approved plans, so it needs its own set, including drawings of the existing structure. On parking, the City’s ADU page waives replacement spaces within a half mile of transit. State law, which the City now applies, goes further: 66314(d)(11) bars requiring replacement of a garage, carport or parking space that is converted or demolished for an ADU. We confirm the City’s reading at the planning consultation.
Review clock and fire zones
As of January 1, 2026, Gov. Code 66317 gives the City 15 business days to tell you in writing whether an ADU application is complete, with a list of anything missing, and 60 days to approve or deny a complete one; a denial or incomplete finding can be appealed. On wildfire mapping, the Salinas Fire Department reported in July 2025 that two areas of the City are mapped as Moderate fire hazard severity zones and that it was starting to adopt that map locally. We check whether a lot falls in one before we specify vents, roofing and siding.
Our work, and where to go next
Everything in our portfolio is from North San Luis Obispo County; we haven’t published a Salinas ADU. To judge our sheets, open the Templeton Modern French Country set, where the permit drawings sit next to photos of the built house. For a broader look at Salinas permits, see home design and drafting in Salinas; for ADU options anywhere we work, see ADU plans and ADU vs junior ADU; and for the sheet-by-sheet basics, what’s in a permit set.
How a Salinas ADU project runs with us
- Parcel check. City or County, zone, lot size, existing structures, easements and the water and sewer providers.
- Route. A pre-approved set, a custom detached or attached unit, a junior unit or a conversion, compared side by side for your lot.
- Drawings. Site plan, floor plans, elevations, structural coordination with an engineer, Title 24 energy forms and the checklist items above.
- Filing and corrections. We upload to the portal and answer plan check comments until the permit is ready to issue.
Salinas ADU FAQ
Does Salinas still have its own ADU ordinance?
Not at the moment. Ordinance 2693, adopted February 24, 2026, removed the City’s ADU section, and the City now processes ADUs under state ADU law until it adopts a new ordinance.
How big can a detached ADU be in Salinas?
Under the state standards the City now applies, a detached unit can reach 1,200 sq ft; we confirm the numbers for your lot at the planning consultation. The four pre-approved plans are 495, 553, 746 and 749 sq ft.
Can I still submit a 2022 version of a pre-approved plan?
No. New applications filed on or after October 1, 2026 need the 2025 editions.
Do I have to live on the property if I add a junior ADU?
Only when the junior ADU shares a bathroom with the house. That change to state law took effect January 1, 2026.
Who signs off besides the City before the permit is issued?
Monterey One Water for sewer and your school district each provide a receipt or waiver, and the deed restriction must be recorded with the County Recorder.
When the permit is in hand
Our sister company Harrod Built (CSLB #986950) builds ADUs and takes work in Salinas. Read about ADUs from Harrod Built or its Salinas page.
Ask about a Salinas ADU
Call 805-712-8993 or use the form. Include the address, whether you’re leaning toward a pre-approved plan or a custom unit, and any survey or past permits you have.
Rules on this page are summarized from City of Salinas Community Development, Permit Services and Fire Department documents, Cal Water and the California Government Code, linked above and checked October 7, 2026. ADU law has shifted several times in two years, so check with the City before you commit to a design.